Skip to content

the Blackout report

What happens when there is no power?

lightning

9 August Blackout – National Grid’s Full Technical Report & Recommendations

Posted on September 6, 2019July 22, 2020 By Chris Owens No Comments on 9 August Blackout – National Grid’s Full Technical Report & Recommendations
Power News

National Grid’s final technical report into August’s blackout calls for review into whether the network has enough backup power to cope with similar incidents.

The 37-page statement submitted by the electricity system operator to energy regulator Ofgem identifies several areas where “lessons can be learned”, including a review into the amount of reserves it holds.

Currently, this backup only needs to be as large as the biggest power plant running on the grid.  

The technical report declares “the processes and procedures in place on 9 August generally worked well to protect the vast majority of customers, there was however significant disruption… Reflecting on the scale of disruption caused to the public, there are some areas where we believe a wider review of policy, processes or procedures may be appropriate.”

What Does The Technical Report Recommend?

National Grid highlights the following areas where lessons can be learned:

  • A review of the security standards (SQSS) to determine whether it would be appropriate to provide for higher levels of resilience in the electricity system. This should be done in a structured way to ensure a proper balancing of risks and costs.
  • The list of facilities connected to the Low Frequency Demand Disconnection (LFDD) scheme should be reviewed to ensure no critical infrastructure or services are inadvertently placed at undue risk of disconnection.
  • Assessing whether it would be appropriate to establish standards for critical infrastructure and services (e.g. hospitals, transport, emergency services) setting out the range of events and conditions on the electricity system that their internal systems should be designed to cater for.
  • As Britain moves to ever increasing levels of embedded generation, a review of the timescales for delivery of the Accelerated Loss of Mains Change Programme to reduce the risk of inadvertent tripping and disconnection of such embedded generation.
  • Review of communication protocols and processes, in particular during the first hour, to support timely and effective communication in any future event.
  • Review of the internal protection systems on electric trains to ensure they can continue to operate through ‘normal’ disturbances on the electricity system.
IN THE DARK: National Grid’s report aims to shine a light on the events of Friday 9 August, when more than 1 million people were left without electricity

The Definitive Version Of What Happened On 9 August

National Grid’s interim report published on 16 August gives its initial account of the events in the lead-up to the blackout.

But with the benefit of a few more weeks’ investigations, the final technical report gives a more detailed analysis of what really happened:

  • At 16:52:33 on Friday 9 August there was a lightning strike on the Eaton Socon-Wymondley 400 kV transmission line. This was one of several lightning strikes that hit the transmission system on the day, but the only one to have a significant impact.
  • The protection systems on the transmission system operated correctly to clear the lightning strike and the associated voltage disturbance was in line with what was expected.
  • The lightning strike initiated the operation of vector shift protection resulting in the tripping of approximately 150 MW of embedded generation.
  • Two almost simultaneous unexpected power losses – at the Hornsea off-shore wind farm (737 MW) and the steam turbine at the Little Barford gas-fired power station (244 MW) – occurred independently of one another, but coincident with the lightning strike. As this generation would not be expected to trip off or de-load in response to a lightning strike, this represents an extremely rare and unexpected event.
  • These events resulted in a cumulative level of power loss greater than the level required to be secured by the Security Standards (1,000 MW based on the largest infeed at the time), and as such a large frequency drop outside the normal range occurred. The frequency drop caused the further tripping of approximately 350 MW of embedded generation.
  • The total loss of generation at this point was 1,481 MW, nevertheless the frequency fall was arrested at 49.1 Hz and began to recover with the deployment of all of the available response and reserve capacity.
  • However, one of the gas turbines at Little Barford then unexpectedly tripped from 210 MW bringing the cumulative loss of generation to 1,691 MW1. There were no further reserves left and the frequency fell to 48.8 Hz.
  • The Low Frequency Demand Disconnection (LFDD) scheme was correctly triggered at 48.8 Hz and automatically disconnected approximately 1.1million customers, totalling almost 1 GW of supplies.
  • The disconnection of demand, coupled with the response and reserve in place along with further dispatch of fast acting plant by ENCC, enabled the frequency return to 50 Hz within 5 minutes.
  • The Distribution Network Operators quickly restored supplies within 40 minutes once the system was in a stable and secure position.
  • Several critical loads were affected for a longer duration by the action of their own systems, in particularly rail services, where disruption extended through Friday evening into Saturday morning. This was due to the fact that approximately 30 trains stopped working and required a technician with a laptop to attend in person to restart, which took significant time. These trains stuck on the tracks caused severe knock-on delays across the rail network.

Find all our coverage about the August 2019 power failure and the fallout from the event here

Tags: 9 August 2019 Blackout Accelerated Loss of Mains Change Programme Distribution Network Operator DNO E3C Energy Emergencies Executive Committee frequency response grid frequency Hornsea Ipswich Hospital LFDD lightning Little Barford Low Frequency Demand Disconnection National Grid National Grid ESO Newcastle International Airport Ofgem Security & Quality of Supply Standard SQSS

Post navigation

❮ Previous Post: The Role Of Battery Storage During The 9 August Blackout
Next Post: Central America Blackout Hits Four Countries ❯

You may also like

Power News
Chicago Blackout Leaves 800,000 In The Dark
August 12, 2020
Power News
Interconnector Failure In France Causes Outages Across Iberian Peninsula
July 26, 2021
flag of kenya next to an electricity pylon
Power News
Trio Of Transmission Line Failures Causes Kenya Power Cut
January 14, 2022
Power News
National Grid ESO Publishes Innovation Strategy 2021-22
March 31, 2021

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Download the blackout report

Latest Comments

  1. 10 Surprising Truths About the Power Grid You Were Never Told - Indian Opinion on Biggest Blackouts In History: South Australia 2016May 28, 2025

    […] Grid inertia—the natural resistance of heavy spinning turbines to speed changes—is critical for maintaining frequency stability. Traditional coal and…

  2. Patrick Mccormick on What Is The Low Frequency Demand Disconnection (LFDD) Scheme?May 22, 2025

    Your writing is so genuine and heartfelt It's refreshing to read a blog that is not trying to sell something…

  3. Tiago on Is The UK Prepared For A Widescale Power Cut? Rating The RiskMay 2, 2025

    Towards what happened in Portugal and Spain last Monday, I’m reading every line you wrote about it. Apparently we suffered…

  4. ‘Unforced Error’: Energy Experts Say ‘Rush To Renewables’ Helped Trip The Switch On Spain’s Grid Crash – Victory MAGA on Biggest Blackouts In History: Italy 2003May 1, 2025

    […] the most significant power outages in European history and is the largest in the region since a 2003 blackout…

  5. ‘Unforced Error’: Energy Experts Say ‘Rush To Renewables’ Helped Trip The Switch On Spain’s Grid Crash – Feeds by OffthePress on Biggest Blackouts In History: Italy 2003May 1, 2025

    […] the most significant power outages in European history and is the largest in the region since a 2003 blackout…

the Blackout report

Get Your Free Report!

Download Now

Tags

9 August 2019 Blackout battery storage Biggest Blackouts in History coronavirus Covid-19 cyberattack cybersecurity distributed energy Distribution Network Operator DNO E3C electricity network electric vehicles Energy Emergencies Executive Committee energy storage Fintan Slye frequency response grid frequency hacking hurricane inertia LFDD lightning load shedding Low Frequency Demand Disconnection malware National Grid National Grid ESO net zero offshore wind Ofgem onshore wind power generation ransomware renewable energy severe weather smart grid solar power storm substation transmission line Ukraine wind wind farm zero carbon

Copyright © 2025 the Blackout report.

Theme: Oceanly News Dark by ScriptsTown